This maintenance KPI calculator works out three key indicators from your work order data: PM compliance, planned work percentage and backlog in weeks. Together they show whether the maintenance team is in control or reacting to breakdowns.
Maintenance KPI formulas
PM compliance (%) = PM tasks completed on time ÷ PM tasks scheduled × 100
Planned work (%) = planned maintenance hours ÷ total maintenance hours × 100
Backlog (weeks) = open backlog hours ÷ weekly labour capacity
Worked example
In one month the team scheduled 120 PM tasks and finished 105 within the allowed window: PM compliance = 87.5 %. Out of 1,600 maintenance hours, 1,150 were planned: planned work = 71.9 %. The open backlog is 900 hours and the team has 360 planned hours a week: backlog = 2.5 weeks.
Main maintenance KPIs and typical targets
Use the MTBF calculator and the OEE calculator for the reliability and production KPIs.
Defining the KPIs clearly
- On time: agree the window, for example within 10 % of the PM interval or within the scheduled week.
- Rescheduled or cancelled PMs: decide whether they count as missed. Hiding missed PMs by moving them makes the KPI meaningless.
- Backlog: count approved work that is ready to be scheduled, in labour hours, and leave out emergency jobs.
How to use the maintenance KPI calculator
Enter the PM tasks scheduled and completed on time in the period, the planned and total maintenance hours, the open backlog in labour hours and the weekly planned labour capacity. Select Calculate to see the three KPIs. A free preventive maintenance Excel template helps you collect the data.
Frequently asked questions
How do you calculate PM compliance?
Divide the number of PM tasks completed on time by the number scheduled in the period, then multiply by 100. 95 done on time out of 100 scheduled is 95 %.
What is a good PM compliance?
Many plants aim for 90 % or more. Below about 80 %, missed PMs usually start to show up as breakdowns.
How do you calculate maintenance backlog?
Add up the estimated labour hours of approved, ready work orders and divide by the planned labour hours available per week. 2 to 4 weeks is a common healthy range.
What are the most important maintenance KPIs?
PM compliance, planned work percentage, schedule compliance, backlog, MTBF, MTTR and OEE are the most widely used.
What is planned vs unplanned maintenance percentage?
Planned work percentage is planned hours divided by total maintenance hours. The rest is unplanned or reactive work. Well-run plants often reach 80 % planned or more.
Related tools and records
Use related calculations with consistent units, periods and equipment scope.
Embed this calculator
Copy this code into your website. The calculator stays free, with a visible attribution link. Visitors can use it without signing up.